Yazd Operation Center, Kahrizsang Telecommunication Building and Iranshahr Flood ‎Control

Previous slide
Next slide

Employer: Iranian Gas Engineering and Development Company

Consultant Engineers: Sazeh Pardazi Iran Consulting Engineers

Contract Price: 744,000,000,000 Rials (Price List 2021)

Contract Duration: 24 Months

Location: Yazd, Isfahan, Sistan va Baloochestan

Type of activity: Construction & Installation, Irrigation and Drainage, Transmission and Distribution of Rural Water

 

The project includes excavation and embankment, building construction and mechanical and electrical installations of the Yazd gas pipeline operation center site with an infrastructure of about 2,870 square meters, including administrative buildings and industrial sheds, a power generator, overhead crane, radiant heater and other equipment, along with landscaping with an infrastructure of 14,151 square meters. The second part is related to the construction of the Kahrizsang telecommunication building of Isfahan with an infrastructure of about 668 square meters with a concrete skeleton. The third part includes the construction of a protective dyke and an earthen dyke with a total length of 1,344 meters around the operation center of the Iranshahr gas pipeline. The following are the most important features of the project:

 

-Excavation and Excavation: 50,400 Cubic Meters

-Framework: 6,100 Square Meters

-Reinforcement: 212 Tons

-Concrete: 2,790 Cubic Meters

-Metal Skeleton: 134 Tons

-Dry Brickwork Rip-Rap: 11,534 Cubic Meters

-Prefabricated Wall: 1,000 Square Meters

-Insulation: 3,150 Square Meters

-Mosaic: 3,930 Square Meters

-Sandwich Panel: 5,420 Square Meters

-Stone Facade: 1,820 Square Meters

-Brick Facade: 1,790 Square Meters

-Base & Sub-base: 2,200 Cubic Meters

-Asphalt: 1,125 Tons

-Electrical Piping: 70 Kilo Meters

-Mechanical Piping: 6 Kilo Meters

-Wiring and Cabling: 44 Kilo Meters