Implementation of architectural operations and mechanical and electrical installations of the MCC structure and adjacent structures of the industrial area and implementation of the MCC building facade using the GFRP method for the

phase two concentration plant project of the Miduk Copper Complex

Previous slide
Next slide

Employer: Canymes Industrial and Mining Engineering Technical Services Company

Consultant Engineers: Sazeh Pardazi Iran Consultant Engineers

Contract Price: 3,734,054,975,794 Rials (Price List of 2025)

Contract Duration: 10 Months

Location: Shahre-Babak

Type of Activity: Construction & Installation

This project includes the main office building with 7 floors and the main shed of the concentration factory with a height of 21.3 meters and several sheds and side buildings with the titles of substation building, main workshop, diesel room, sports house, general building, main laboratory, mechanical room and silo with a substructure of 17894 square meters located in Mes Midok, Shahre-Babak city of Kerman province. One of the most important features of the project is the dry GFRP polymer facade with an area of about 6000 square meters. Also, other features of the project can be mentioned:

Concrete: 2,556 Cubic Meters

Concrete Hardening Mortar Application: 6185 Square Meters

Brickwork with Pressed Bricks: 1,909 Cubic Meters

Double Sided Brick façade: 9,475 Square Meters

Autoclaved Block construction: 18,652 Square Meters

Moisture Insulation: 9,004 Square Meters

Lightweight Steel Works: 270 Tons

Ceiling & Wall Sandwich Panels: 7,371 Square Meters

Cement Coating: 21,397 Square Meters

Mosaic: 4,691 Square Meters

Tiles: 6,500 Square Meters

Epoxy Flooring: 14,857 Square Meters

Acrylic Paint: 10,494 Square Meters

Ducting: 4,325 Square Meters

Mechanical & Electrical Piping: 20,015 Meters Long

Cabling & Wiring: 12,130 Meters Long

Different Types of Lights: 5,074 Pieces