The project encompasses earth-filling operations, the fabrication and erection of the steel structure, structural and finishing works, and all mechanical and electrical installations for a main building with a floor area of 17,800 square meters (spanning seven stories), as well as landscaping covering an area of over 6,500 square meters.
The building’s mechanical system comprises an air-cooled chiller, hot water boilers, air handling units (AHUs), and fan coil units. Key project specifications include the following:
– Excavation and earth-filling: 15,000 m³
– Steel structure: 1,867 tons
– Permanent steel decking: 211 tons
– Concrete wall formwork: 1,500 m²
– Reinforcement (rebar) work: 300 tons
– Concrete pouring: 6,000 m³
– Lightweight cement block walling: 8,000 m²
– Stonework: 23,000 m²
– Electrical and mechanical piping: 50 km
– Ductwork: 2,600 m²