The project encompasses earthworks, the concrete structural frame, structural masonry and finishing works, as well as all mechanical and electrical installations. The main building—featuring a total floor area of approximately 9,891 square meters distributed across three blocks ranging from one to five stories—includes a helipad. Additionally, the project comprises ancillary buildings with a floor area of about 900 square meters, along with perimeter fencing and landscaping covering an area exceeding 21,200 square meters. The building’s mechanical system consists of an integrated air-cooled chiller, hot water boilers, air handling units, and fan coil units; key project specifications include the following:
- Excavation and earthfilling: 32,200 cubic meters
- Formwork: 29,500 square meters
- Reinforcement (rebar) work: 900 tons
- Concrete: 11,500 cubic meters
- Knauf (drywall) walls and ceilings: 25,000 square meters
- Stone masonry: 8,350 square meters
- Tiling: 2,300 square meters
- Electrical and mechanical piping: 90 kilometers
- Wiring and cabling: 132 kilometers