The joint facilities for Golgohar and Gohar Zamin are situated on a 17,000-square-meter site. The project encompasses earthworks, concrete structural framing, structural masonry and finishing works, as well as all mechanical and electrical installations for the following structures: a main administrative building (600 m²); dedicated administrative buildings for Golgohar and Gohar Zamin (180 m² each); a restaurant (379 m²); a shift service building (487 m²); and a mechanical plant building (166 m²). Additionally, the project includes two industrial sheds, each measuring 1,200 m² (totaling 2,400 m²). The mechanical systems feature cast-iron hot water boilers, radiators, and split-system air conditioning units. Key project specifications include the following:
Excavation and earthfill: 9,000 m³
Concrete pouring: 2,800 m³
Armelat flooring: 2,400 m²
Steel shed structure: 404 tons
Light steel works: 160 tons
Brick facade: 3,300 m²
Leca block masonry: 6,000 m²
Sandwich panels: 5,860 m²
Tiles and ceramics: 2,000 m²
Mosaic flooring: 1,830 m²
Sub-base and base course: 2,350 m³
Asphalt paving: 6,600 m²
Wiring and cabling: 22 km
Floodlights: 60 units
Electrical and mechanical piping: 13 km